Wednesday, August 22, 2012

More Progress on the House

(cycle 24, day 8)

side note: i was really trying not to count actual cycle days and just know what day we need to start BDing and that we should do that for a week, is totally working against me, lol.

anyway...

i should mention the ordeal DH went through to get the sewer line tied in... sheesh. we didn't think it would be more than 9 or 10 feet in the ground and had a general idea where it would be. well we were in the right area, but it took us (well him) 3 days to find it  :/  the first day, he spent about 4 hours digging and moving dirt around hoping to find it with no luck and then had a bday part to go to so he put it on hold til the next day. the next day wasn't any more successful. after another couple hours looking for the sewer line and a lot of frustration later, he abondoned the hole for another night. he did have his plumber buddy come over to give him an idea of where it would be. he looked down the main in the road and said it was pretty deep so we probably had a few extra feet left to dig... that could not have been more true. DH found it within about 45 minutes that morning, 13 FEET IN THE GROUND! the machine hoe we had only reaches about 12' directly below itself and since there was already a hole there, he had to do it by hand. such a pain in the ass. didn't help that the hole kept filling with water so he was battling that along with the mud at the bottom giving way under his feet so he didn't have a solid footing. he finally got the fiting in and quickly got to filling the hole back up. we'll definately be hiring someone if we ever need to do that again.... worst idea ever!!!

so fast forward about a week and we started trenching in the garage to run the sewer and electrical lines in the ground and thinking we would be protected from weather... YEAH RIGHT! apparently walls and a floor overhead doesn't stop driving rain from coming it and making a mess of everything  :(  so we had to abandon that ship for another day as there was so much rain coming down it was soaking the ground within 2 or so feet of the doors... not fun. we got back to working on that another day with better success. of course if my DH had even the slightest bit of patience, none of these things that go wrong would seem as bad as they do, but since patience is his nemisis things get blown out of proportion  :P  so we worked on the sewer line and it was hot out so every little annoyance turned into the end of the world, but we got it done  :)

concrete should be getting poured in the next day or two!!! so that also means we'll be getting the windows and doors in the addition in the next week or so when our framer comes back (and possibly the windows and doors in the existing house if we ask him nicely and pay him...). at that point, we can start running electrical lines and the plumbing runs and get those inspections done. and then we can move on to insulation, vapour barrier and drywall, ah!

with the garage slab going in this week, we'll also be getting someone to grade the front yard/driveway and then we can get the driveway poured which is super exciting because we haven't had a driveway in 3 months (4 by the time we can drive on it), lol. we're also hoping to get someone to do the siding and such in september/october so that will wrap up the outside work until the spring  :)

our new furnace is also getting installed. it would have been this week, but the wrong coil thingy for the A/C option was wrong, so they have to wait for the right part to come in next week and they can finish that up. the nights sure are getting cold and it would be nice to turn it back on.

i still have yet to get a pic of the house with all the shingles on the roof... for now, i'll just throw in some other pics of various things having to do with the addition  :)
master bedroom framing
sewer plumbing to existing sewer line
new electrical panel and conduit running
to the panel inside the house

No comments:

Post a Comment